Snagging and Defect Claims Against Dubai Developers
7 min read
Posted on November 23, 2026
The snagging report ran to forty items. The developer closed eleven of them, called the rest cosmetic and stopped replying. Eight months later the bathroom leak that was listed as a tile issue has reached the apartment below.
Snagging and defect claims in Dubai run on two separate clocks that most owners discover only after one of them has stopped. The clocks come from Article 40 of Law No. 6 of 2019 Concerning Ownership of Jointly Owned Real Property in the Emirate of Dubai, which applies to property held under the jointly owned regime rather than to every building in the city.
Two Clocks, Not One
Article 40(a) makes the developer responsible for remedying or rectifying defects in the structural parts of the jointly owned real property for ten years, running from the date he obtains the completion certificate.
Article 40(b) is the shorter one and the one that expires while people are still exchanging emails. The developer remains liable for repairing or replacing defective installations for one year from the handover of the unit to the owner, covering mechanical and electrical works along with sanitary and sewerage installations. Where the owner does not take possession, that year runs from the completion certificate instead.
The technical items on a snagging list sit in that second category. Air conditioning that does not cool, a water heater that trips, drainage that backs up and sockets that are dead are installations rather than structure, so they carry twelve months rather than ten years. A developer who responds slowly for eleven months on those items has not necessarily been obstructive. He has been effective.
The finishing items are a separate question. Paint, tiling, joinery, doors and general workmanship are not installations and Article 40(b) does not name them, so a claim on those runs through the sale agreement and the general law on a defective thing sold rather than through Article 40. Splitting the list along that line is the first piece of work on any of these files.
The Liability That Cannot Be Signed Away
Article 40(d) provides that any agreement to the contrary made after the law came into force is null and void. A handover document in which the owner accepts the unit in its current condition and waives further claims does not displace the ten year and one year periods.
Article 40(c) preserves any other rights or warranties an owner holds under other legislation, so the Article 40 periods sit on top of whatever the sale agreement and the general law give rather than replacing them.
That combination is worth knowing at the moment of handover, when the pressure to sign quickly and collect the keys is highest.
The Ten Years Behind the Ten Years
Underneath the Dubai provision sits the decennial liability regime in the Civil Transactions Law. Article 821 makes the engineer who designed a building and the contractor who built it under his supervision jointly and severally liable for total or partial collapse within ten years, even where the cause was a defect in the land itself or the employer approved the defective work. Article 821(2) extends that guarantee to defects that threaten the solidity and safety of the structure. Article 821(3) runs the ten years from the point the employer takes delivery.
Article 822 divides the engineer's exposure by what he was engaged to do. An engineer who only produced the design answers for design defects rather than for how the work was carried out. An engineer who only supervised execution is jointly liable with the contractor for execution defects that happened under his supervision. Article 823 makes void any condition intended to exempt the engineer or the contractor from that guarantee or to limit it.
The limit of this regime for a unit owner is the relationship it attaches to. It runs between the employer and the professionals he engaged, so where the developer commissioned the building it is the developer who holds that claim against his contractor. An owner's claim is against the developer, under Article 40 and under the sale agreement. The decennial regime matters to him because it is what stands behind the developer rather than because it hands him a direct route.
Those article numbers come from Federal Decree-Law No. 25 of 2025, in force since 1 June 2026. The provisions it replaced were Articles 880 to 883. Article 4 provides that the new law does not apply retroactively to preceding facts and acts, while Articles 6 and 7 carry separate rules for limitation periods running across the date. On a construction file that means four dates are established before any article number is cited: the contracting agreement, delivery, the defect or the collapse and the point at which the claim accrued.
Three Years Is the Deadline That Catches People
Article 824 provides that a guarantee claim will not be heard after three years from the collapse or from the discovery of the defect.
Owners read the ten years and assume they have ten years to act. The ten years is the window during which a defect appearing triggers liability. The three years is the window for bringing the claim once that defect has collapsed something or been discovered. A structural crack found in year three and argued about until year seven has exhausted the second period while the first was still running.
This is the single most useful thing on this subject to know early, because it is a deadline that runs quietly while correspondence continues.
Where the Defect Makes the Unit Unusable
For an off-plan purchase there is a further route. Article 20 of Executive Council Resolution No. 6 of 2010, the Implementing Bylaw of Law No. 13 of 2008, allows a purchaser to apply to the competent court to terminate the contract where it is proven after handover that the unit is unfit for use because of material construction defects.
That is a high threshold and it is aimed at a different outcome from a repair claim. It is worth identifying early, because a file run for eighteen months as a complaint about finishes is harder to re-present as a unit that was never fit for use.
A File That Turns on the Handover Date
An owner takes handover in March and signs the handover form the same day. The snagging report is submitted in April. The developer rectifies some items through the summer. In April of the following year the air conditioning fails completely and the developer replies that the warranty period has ended.
On the installations the developer is right, because thirteen months have passed and the March handover date is what started the clock. When a matter of this kind reaches me as a Legal Consultant, the assessment starts with six things:
- The date of the completion certificate and the date of handover of the unit, which start the two different periods
- Whether each item on the list is structural or an installation, because they are on different clocks
- The snagging report, its submission date and every reply to it
- Whether the defect has been formally notified rather than discussed, with the date it was first reported
- When the defect was discovered, since Article 824 runs from discovery rather than from handover
- Whether the property is held under the jointly owned regime, because Article 40 is written for that regime
The habit that costs owners most is treating a defect as a service problem to be chased rather than a claim with a date on it. A polite reminder sent every month for a year and a formal notice served in month two look much the same in an inbox. They are not the same document once the three years is being counted.